Budimex says Kutřín dry flood reservoir dam construction reaches 75% completion
Budimex reached about 75% completion on a dry flood retention reservoir in Kutřín, Czech Republic, for state-owned Povodí Labe. Reinforced-concrete dam works are about 75% complete; mechanical equipment installation has started; commissioning targeted for mid-next year. Project capacity set at 3,600,000 cubic meters; m