Equinor raises Snohvit Future cost estimate to NOK 26.5 billion

Equinor lifted the Snohvit Future cost estimate to NOK 26.5 billion in 2026 value. Schedule held unchanged, with onshore compression start planned for 2029. Electrification of Hammerfest LNG still targeted for 2030.