Endeavour Silver expects about three weeks of reduced processing at its Guanacevi mine after taking the primary ball mill offline to replace the mill head and trunnion. Throughput is expected at ~600 tpd versus ~1,100 tpd; mining continues and parts are on site.

EDR

Endeavour Silver expects about three weeks of reduced processing at its Guanacevi mine after taking the primary ball mill offline to replace the mill head and trunnion. Throughput is expected at ~600 tpd versus ~1,100 tpd, while mining continues and parts are on site.